NEWS RELEASE: 18th Avenue NW Reconstruction Project to Resume

Post Date:04/10/2018

Contact: Megan Moeller
Public Works Communications Coordinator
507-328-2436 or mmoeller@rochestermn.gov
Dillon Dombrovski
Public Works Construction Project Manager
507-328-2421 or ddombrovski@rochestermn.gov

The reconstruction of 18th Avenue NW (CR 112) is set to resume on April 16, 2018, weather permitting. Stage 1 of this project will completely close the road from 55th Street NW to 45th Street NW and no through traffic will be allowed. Local traffic only” from 55th Street NW will be able to access Royal Place NW to the funeral home and daycare located on this street.

Project Timeline
This construction project is scheduled to begin on April 16, 2018 and has an anticipated completion date of October 31, 2018. Stage 1 work, which encompasses 55th Street NW to 45th Street NW, will resume where the project left off last year. In conjunction with Stage 1 construction, Stage 4 will be started from 41st Street NW to 37th Street NW sometime in May. The start of Stage 2 and Stage 3 from 45th Street NW to 41 Street NW will be announced at a later date once Stage 1 is complete. *All dates are weather dependent and subject to change.

Project Impacts
This project will have a major impact on those who travel this corridor. Complete road closures will be common. When possible, local access into the neighborhoods and businesses will be maintained. The official detour route is along West River Parkway past Essex Park and the Watson soccer fields. See provided map.

Pedestrian access will remain at existing locations, except when the new sidewalks/paths are being constructed, at which time an alternate pedestrian route will be established. There are currently no pedestrian facilities beyond 45th Street NW. The completed project will provide continuous pedestrian facilities on both the east and west sides of 18th Avenue NW to 55th Street NW.

Rochester Public Transit (RPT) Route 26 Outbound will detour by using 48 St NW to 22 Ave NW, then south on 22 Ave NW to East Frontage Rd NW, and north to 55 St NW, where it will resume its regular path. The Inbound 26 will travel this detour in reverse. Visit www.rptride.com for maps and any further details about the effect this project will have on transit.

Project Benefits
18th Avenue NW, also known as County Road (CR) 112, provides a critical connection in the growing northwest corner of Rochester. As the community has grown north to 55th Street NW and beyond, the traffic on 18th Avenue NW has also increased. The goal of this project is to reconstruct 18th Avenue NW to improve the function and safety of the roadway for pedestrians, bicycles, transit and vehicles while better serving the surrounding urbanizing land uses.

The proposed project will:
• Reconstruct 18th Avenue NW (CR 112) from 37th Street NW to 55th Street NW. This involves the complete removal and replacement of the entire street section.
• Enhance pedestrian and bicycle traffic facilities, including 10 foot wide off-street multi-use paths and 6 foot wide bike lanes.
• Improve the safety and flow of traffic through the corridor by adding a mini-roundabout at the 48th Street intersection and turn lanes at other high volume intersections.
• Replace existing signal systems to include flashing yellows turn signals and pedestrian crossings with APS signals that are compliant with ADA (American Disability Act) Standards. Accessible Pedestrian Signals (APS) are audible signals that communicate information about the WALK and DON’T WALK intervals at signalized intersections in non-visual formats to pedestrians who are blind or who have low vision.
• Provide an opportunity for maintenance and repairs to aging sanitary sewer and water main utilities, as well as, upgrades to stormwater management infrastructure to better treat runoff and protect area waterways.
• Add landscaping, including boulevard trees, boulevard rain gardens, raised medians with grass and plantings.

Project Funding
This project is being funded, in part, by $4,365,925 in Federal Funds. The remaining costs are being shared by the City of Rochester and Olmsted County. Historically, this road (CR 112) was the responsibility of Olmsted County. Upon completion of this work, the roadway will be transferred to the City of Rochester.

For more information on the project planning and design that led to this construction project, please visit https://www.bolton-menk.com/clients/rochester/index.html
http://www.rochestermn.gov/departments/public-works/construction-projects/current-projects

Pedestrians and drivers are advised to use caution while traveling around and through all construction zones. The cooperation and patience of the public is greatly appreciated during construction. You can also assist by keeping children away from the work zone.

Follow us on Facebook: @RochesterMNPublicWorksDepartment

News Release Full Version