| Parks 2008-2013 Capital Improvements Program | Schedule for Six Year Period | |||||||||||||||
| a = Special assessment Bonds ad = Abatement District c = County | eu = Electric Utility f = Federal fr = Flood Control Reserves | |||||||||||||||
| fb = Food & Beverage Tax go = General Obligation Bonds gs = Golf Surplus Park & Rec Fund | lt = Lodging Tax ms = MN State Aid-Streets ot = Operating Transfer-General Fund | |||||||||||||||
| p = Private Funds pc = Passenger Facility Charges r = Project Reserves | rb = GO Revenue Bonds re = Retained Earnings s = State | |||||||||||||||
| sa = Sn/Sewer Availability Chg sl = State Loan Fund st = Sales Tax | sw = Storm Water Mgmt Chg t = Tax Levy td = Traffic Improvement Dist Chg | |||||||||||||||
| ti = Tax Increments to = Operating Trnsfrs-Other Fnds wa = Water Availability Chg | wu = Water Utility | |||||||||||||||
| Sort | Map # | Project Description | Proj # | Total Cost | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | ||||||
| 0 | ||||||||||||||||
| 1 | 1 | Cascade Lake Park. This project consists of consultant services and construction. Initial landscaping of the north side of the lake in 2008 ($20,000), trail construction 2008-2009 on the north side of the lake ($750,000), beach area grading plan in 2008 ($20,000), shaping and grading the Mayo cell penninsula and park area adjacent to control structure 2010, parking facilities and continued landscaping in 2011 and beach area grading 2011. | 2981 | 2,410,000 | 25,000 | t | 100,000 | t | 100,000 | t | 300,000 | t | 300,000 | t | 275,000 | t |
| 1 | 850,000 | fr | 50,000 | fr | 150,000 | fr | ||||||||||
| 1 | 260,000 | r | ||||||||||||||
| 1 | ||||||||||||||||
| 2 | 2 | Rochester Baseball Complex projects include irrigation ($30,000) and open shelter ($50,000) in common area adjacent to concession building. Partial funding by RYBA. The private funds from 2008-2011 is RYBA's repayment of funds used to light fields in 2005. | 2890 | 430,000 | 35,000 | t | 40,000 | t | 40,000 | t | 45,000 | t | 25,000 | t | 25,000 | t |
| 2 | 35,000 | p | 35,000 | p | 35,000 | p | 40,000 | p | 75,000 | p | ||||||
| 2 | ||||||||||||||||
| 3 | 3 | Plummer House improvements. This project consists of boiler and roof replacement, tuck pointing and replacement of water pipes. | 2980 | 205,000 | 30,000 | t | 20,000 | t | 25,000 | t | 30,000 | t | 40,000 | t | 50,000 | t |
| 3 | 10,000 | r | ||||||||||||||
| 3 | ||||||||||||||||
| 4 | 4 | Reforestation of city parks / public lands and boulevards in anticipation of significant tree losses due to Emerald Ash Borer. | 3033 | 300,000 | 25,000 | t | 35,000 | t | 45,000 | t | 55,000 | t | 65,000 | t | 75,000 | t |
| 4 | ||||||||||||||||
| 5 | 5 | Kutzky Tennis Center improvements include repairs to clubhouse and 15 courts, replace wind screen and nets and re-roof the building | 2905 | 224,500 | 44,500 | r | 25,000 | t | 30,000 | t | 35,000 | t | 40,000 | t | 50,000 | t |
| 5 | ||||||||||||||||
| 6 | 6 | Central Park Heritage House roof replacement | 2933 | 29,500 | 17,000 | r | 2,500 | t | 2,500 | t | 2,500 | t | 2,500 | t | 2,500 | t |
| 6 | ||||||||||||||||
| 7 | 7 | Tennis Court improvements. This project includes the repair and replacement of 17 pairs of tennis courts located throughout the city. | 2944 | 210,000 | 30,000 | r | 40,000 | t | 20,000 | t | 25,000 | t | 40,000 | t | 55,000 | t |
| 7 | ||||||||||||||||
| 8 | 8 | East Park improvements includes construction of permanent storage building and restroom facilities. | 3027 | 207,000 | 7,000 | r | 15,000 | t | 20,000 | t | 35,000 | t | 60,000 | t | 70,000 | t |
| 8 | ||||||||||||||||
| 9 | 9 | Park acquisition and development. To provide funding for acquisition and development of park lands not identified on the master acquisition plan. | 2899 | 320,000 | 20,000 | r | 10,000 | t | 15,000 | t | 20,000 | t | 30,000 | t | 45,000 | t |
| 9 | 40,000 | r | 60,000 | r | 80,000 | r | ||||||||||
| 9 | ||||||||||||||||
| 10 | 10 | Quarry Hill Park / Quarry Hill Nature Center. This projects includes phase II of replacing roofing (2011), and enclosing exterior stone chimney (2008), park and trail signage (2008) | 2913 | 230,000 | 20,000 | t | 45,000 | t | 25,000 | t | 30,000 | t | 50,000 | t | 50,000 | t |
| 10 | 10,000 | r | ||||||||||||||
| 10 | ||||||||||||||||
| 11 | 11 | Restoration of prairie involving vegetation management and establishment of prairie in city parks and on other city owned lands. | 3003 | 70,000 | 5,000 | r | 10,000 | t | 10,000 | t | 15,000 | t | 15,000 | t | 15,000 | t |
| 11 | ||||||||||||||||
| 12 | 12 | Kutzky Park improvements include replacement of shelter (2009-$165,000) and irrigation of football field (2008-$20,000). | 3031 | 220,000 | 20,000 | r | 25,000 | t | 30,000 | t | 45,000 | t | 50,000 | t | 50,000 | t |
| 12 | ||||||||||||||||
| 13 | 13 | Ridge View Manor Park. This project includes general site work and landscaping and trail from 65 St and to Douglas Trail . Transfer $25,000 from NW2898 dedication funds. | 2874 | 216,000 | 51,000 | r | 10,000 | t | 20,000 | t | 30,000 | t | 40,000 | t | 65,000 | t |
| 13 | ||||||||||||||||
| 14 | 14 | SE Youth Softball Complex consists of the development of a 5 field complex at the intersection of TH 14 and 36 Ave SE. Private funds from Youth Softball Association to repay City for 2007 construction of fields. Transfer $5,000 from the F E Williams Fund. | 3025 | 315,000 | 61,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | ||
| 14 | 25,000 | p | 25,000 | p | 25,000 | p | 25,000 | p | 49,000 | p | ||||||
| 14 | 5,000 | to | ||||||||||||||
| 14 | ||||||||||||||||
| 15 | 15 | Park/Forestry operations center improvements. This project consists of replacement of floor surfaces in leased spaces, adding restrooms and crew rooms, and an equipment wash bay. | 2928 | 152,000 | 52,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | ||
| 15 | ||||||||||||||||
| 15 | ||||||||||||||||
| 16 | 16 | Silver Lake Park improvements include continued remodeling of West Silver Lake shelter, irrigating baseball field ($20,000), and replacing the playground on the east side of the park ($50,000). | 3012 | 110,000 | 40,000 | r | 20,000 | t | 25,000 | t | 25,000 | t | ||||
| 16 | ||||||||||||||||
| 17 | 17 | Essex Park projects include repairs to caretaker's quarters in 2008 ($5,000), construction of a storage building and development of site for staging park operations on the north side of the City and conversion of 30 acres to native grasses / prairie. | 2950 | 442,000 | 52,000 | r | 70,000 | t | 100,000 | t | 100,000 | t | 120,000 | t | ||
| 17 | ||||||||||||||||
| 18 | 18 | McQuillan Field improvements includes continued replacement of field fencing in 2008 ($25,000) and the planning and development of 40 acres south of existing fields | 2962 | 230,000 | 25,000 | t | 40,000 | t | 45,000 | t | 50,000 | t | 60,000 | t | ||
| 18 | 10,000 | r | ||||||||||||||
| 18 | ||||||||||||||||
| 19 | 19 | Development and improvement of park drives and parking lots. | 2909 | 287,000 | 137,000 | r | 50,000 | t | 50,000 | t | 50,000 | t | ||||
| 19 | ||||||||||||||||
| 20 | 20 | Mayo Field improvements. The project consists of repainting the grandstand, relighting the field, and replacing spectator fencing. | 2914 | 230,000 | 30,000 | t | 25,000 | t | 30,000 | t | 50,000 | t | 35,000 | t | ||
| 20 | 60,000 | r | ||||||||||||||
| 20 | ||||||||||||||||
| 21 | 21 | Soldier's Field Park improvements. This project includes the addition of a canopy shelter south of new restroom (2010), upgrade of softball field fencing (2008), and football field lighting (2011). | 2878 | 225,000 | 25,000 | t | 35,000 | t | 40,000 | t | 70,000 | t | 55,000 | t | ||
| 21 | ||||||||||||||||
| 22 | 22 | Eastwood Park / 100 Acre Woods site development and equipment. | 3020 | 110,000 | 20,000 | r | 30,000 | t | 30,000 | t | 30,000 | t | ||||
| 22 | ||||||||||||||||
| 23 | 23 | Weatherstone Park development. This project consists of site work and trails, including a connection to the Douglas Trail. | 2883 | 134,000 | 59,000 | r | 35,000 | t | 40,000 | t | ||||||
| 23 | ||||||||||||||||
| 24 | 24 | Fox Trail Park and related neighborhood park development on KR reservoir, including trails, playground equipment, and landscaping. | 3018 | 75,000 | 25,000 | r | 25,000 | t | 25,000 | t | ||||||
| 24 | ||||||||||||||||
| 25 | 25 | Pinewood Ridge Park development. This project consists of site work, landscaping, trails, and playground equipment. | 3021 | 110,000 | 45,000 | t | 10,000 | t | 10,000 | t | ||||||
| 25 | 45,000 | r | ||||||||||||||
| 25 | ||||||||||||||||
| 26 | 26 | Pinewood Hills Park development. This project consists of grading, field construction, and playground equipment. | 3019 | 90,000 | 60,000 | r | 15,000 | t | 15,000 | t | ||||||
| 26 | ||||||||||||||||
| 27 | 27 | Hart Farms Park development. This project consists of access paths, sidewalk installation, landscaping and sports field construction. Transfer reserves of $30,000 from SW 2897 dedication funds. | 3005 | 61,000 | 36,000 | r | 10,000 | t | 15,000 | t | ||||||
| 27 | ||||||||||||||||
| 28 | 28 | Scenic Oaks Park development. Includes access paths, sidewalks and field construction. Transfer reserves of $25,000 from SW 2897 dedication funds. | 3006 | 84,000 | 54,000 | r | 15,000 | t | 15,000 | t | ||||||
| 28 | ||||||||||||||||
| 29 | 29 | Summit Pointe Park development access paths and landscaping | 2881 | 28,500 | 13,500 | r | 15,000 | t | ||||||||
| 29 | ||||||||||||||||
| 30 | 30 | Fencing / Backstop replacements at Lutheran School and Zumbro Park South. | 2888 | 28,000 | 13,000 | r | 15,000 | t | ||||||||
| 30 | ||||||||||||||||
| 31 | 31 | Adventure Playground in Silver Lake Park includes replacement of playground surfacing. | 2988 | 115,000 | 65,000 | t | 25,000 | t | ||||||||
| 31 | 25,000 | r | ||||||||||||||
| 31 | ||||||||||||||||
| 32 | 32 | Fieldstone Park development. This project consists of play field, landscaping, and playground equipment. | 3030 | 75,000 | 25,000 | r | 50,000 | t | ||||||||
| 32 | ||||||||||||||||
| 33 | 33 | Foster Arend Park project includes replacement of playground equipment on the beach. | 2958 | 14,500 | 14,500 | r | ||||||||||
| 33 | ||||||||||||||||
| 34 | 34 | Northern Slopes Park playground replacement | 3010 | 35,000 | 35,000 | r | ||||||||||
| 34 | ||||||||||||||||
| 35 | 35 | Schmidt Park improvements consists of the development of the school/park site as an interim neighborhood park. | 2990 | 242,000 | 7,000 | r | 40,000 | t | 50,000 | t | 50,000 | t | 95,000 | t | ||
| 35 | ||||||||||||||||
| 36 | 36 | West Diamond Ridge Park development. Includes grading, seeding, playground equipment, ball diamonds, and parking lot. | 3002 | 162,000 | 27,000 | r | 20,000 | t | 30,000 | t | 40,000 | t | 45,000 | t | ||
| 36 | ||||||||||||||||
| 37 | 37 | Harvest View Park development. This project consists of site work, playground equipment, and site furniture. This park to be developed jointly with the adjacent elementary school site. | 200,000 | 50,000 | t | 50,000 | t | 50,000 | t | 50,000 | t | |||||
| 37 | ||||||||||||||||
| 38 | 38 | Stonehedge Estates Park development. This project consists of trails and the development of a neighborhood park in the subdivision. | 3007 | 62,700 | 12,700 | r | 15,000 | t | 15,000 | t | 20,000 | t | ||||
| 38 | ||||||||||||||||
| 39 | 39 | Development of Lincolnshire Park. The development of 23 acres of athletic fields, ice rink, warming house and trail connecting the park to Douglas Trail. Concrete rink pad in 2008, year round boards and lighting followed by warming house in 2010. | 2959 | 250,000 | 250,000 | r | ||||||||||
| 39 | ||||||||||||||||
| 40 | 40 | Badger Hills Park development. This project consists of the development of a six acre site with a playfield and playground equipment. Transfer reserves of $50,000 from NW 2898 dedication funds. | 3028 | 103,000 | 103,000 | r | ||||||||||
| 40 | ||||||||||||||||
| 41 | 41 | Meadow Park replacement of playground equipment. | 3011 | 50,000 | 50,000 | t | ||||||||||
| 41 | ||||||||||||||||
| 42 | 42 | Silver Lake Pool improvements. This project consists of recoating pool walls, reroofing, a new filtration system, and repairs to the facility. | 2904 | 100,000 | 25,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | ||||
| 42 | ||||||||||||||||
| 43 | 43 | Century Hills South Park development includes playground equipment and landscaping. | 100,000 | 25,000 | t | 25,000 | t | 25,000 | t | 25,000 | t | |||||
| 43 | ||||||||||||||||
| 44 | 44 | Roy Watson Youth Sports Complex development. This project includes paths and hard surfacing ball diamond plaza area. | 2972 | 291,000 | 80,000 | t | 30,000 | t | 50,000 | t | 100,000 | t | ||||
| 44 | 31,000 | r | ||||||||||||||
| 44 | ||||||||||||||||
| 45 | 45 | Morris Hills Park development. This project consists of site development to start in 2008 and equipment in 2009. | 3017 | 210,000 | 40,000 | t | 40,000 | t | 40,000 | t | 45,000 | t | ||||
| 45 | 45,000 | r | ||||||||||||||
| 45 | ||||||||||||||||
| 46 | 46 | Prairie Crossing Woodland Park development. Includes trails and site work. | 75,000 | 25,000 | t | 25,000 | t | 25,000 | t | |||||||
| 46 | ||||||||||||||||
| 47 | 47 | Faud Monsour Youth Athletic Field Complex development includes construction of the parking area south of Heinz center, relocating two fields and irrigation and pond. | 2951 | 125,000 | 30,000 | t | 40,000 | t | 55,000 | t | ||||||
| 47 | ||||||||||||||||
| 48 | 48 | Bamber Valley Estates Park development. This project consists of site work, landscaping, and playground equipment. | 80,000 | 20,000 | t | 30,000 | t | 30,000 | t | |||||||
| 48 | ||||||||||||||||
| 49 | 49 | Bamber Ridge Park replacement of playground equipment. | 55,000 | 15,000 | t | 20,000 | t | 20,000 | t | |||||||
| 49 | ||||||||||||||||
| 50 | 50 | Elmcroft Park projects include playground and backstop replacement. | 3016 | 50,000 | 50,000 | t | ||||||||||
| 50 | ||||||||||||||||
| 51 | 51 | Crimson Ridge corridor trail development from 55 Street to 65 Street NW. | 75,000 | 25,000 | t | 25,000 | t | 25,000 | t | |||||||
| 51 | ||||||||||||||||
| 52 | 52 | Soldier's Field pool shade canopy and other improvements. | 2956 | 80,000 | 20,000 | t | 30,000 | t | 30,000 | t | ||||||
| 52 | ||||||||||||||||
| 53 | 53 | Forest Knoll Park development. This project consists of the development of a seven acre site with a playfield, trail access, and playground equipment. | 175,000 | 50,000 | t | 50,000 | t | 75,000 | t | |||||||
| 53 | ||||||||||||||||
| 54 | 54 | Northern Heights Village Park development. This project consists of grading and playground equipment on a four acre site. | 120,000 | 40,000 | t | 40,000 | t | 40,000 | t | |||||||
| 54 | ||||||||||||||||
| 55 | 55 | Stone Gate Summit Park development includes playground and site work. | 120,000 | < | ||||||||||||