Streets shall be graded to the full width of the right-of-way in accordance with grades submitted to and approved by the City Engineer.  All street grading and gravel base construction shall be in accordance with approved plans.  Where necessary, street grading shall be completed prior to the installation of applicable underground utilities, and gravel base construction undertaken after the installation of the utilities.


64.211

Construction to be Consistent with Engineering Standards: Following the City Engineer's approval of street grading and utility installation, streets shall be surfaced and provided with adequate stormwater facilities consistent with the engineering standards adopted by Public Works in conjunction with the development of subdivisions.