Current Projects

Print
Press Enter to show all options, press Tab go to next option

Construction Activity


1st Avenue NE/SE Sanitary Sewer Relief Line Phase A J7825 and Rochester Parking Ramp No.6 J2582

Road Closure Maps:

Overall Project Manager: John Pristash, Kraus-Anderson Construction Company (507-218-2639)
Sewer Project Manager: Matt Crawford, Public Works
Sewer Project Inspector: Eric Loftus, Public Works

**Click here for information on the Hilton Hotel Project that is in this same area**


4th Street SW Reconstruction from 1st Avenue SW to 6th Avenue SW - J7326

The project will reconstruct 4th Street SW, from 1st Avenue to 6th Avenue, to address the pavement that is in poor condition, to add bicycle facilities and to upgrade the sanitary sewer. Once the project concept is established final design will occur in early 2018 the project will be constructed from April – October 2018.

Learn more at the project website: https://rochester4thst.wpengine.com/project-summary/


18th Avenue NW (CR 112) Reconstruction from 37th Street NW to 55th Street NW – J7813

18th Avenue NW, also known as County Road (CR) 112, provides a critical connection in the growing northwest corner of Rochester. As the community has grown north to 55th Street NW and beyond, the traffic on 18th Avenue NW has also increased. The goal of this project is to reconstruct 18th Avenue NW to improve the function and safety of the roadway for pedestrians, bicycles, transit and vehicles while better serving the surrounding urbanizing land uses.

The proposed project includes reconstruction of 18th Avenue NW (CR 112) from 37th Street NW to Royal Place NW and pavement rehabilitation from Royal Place NW to 55th Street NW. The proposed project will replace deteriorated pavement, replace existing signal systems, address aging sanitary sewer and water main utilities, provide pedestrian enhancements, improve the storm drainage system, construct an urban section with a mini roundabout, add bike lanes, and add landscaped medians for access management improvements.

For more information on the project planning and design that led to this construction project, please visit Bolton-Menk 18th Avenue NW (CR112) Reconstruction Project

Project Updates

Project Manager/Construction Manager: Dillon Dombrovski, Public Works
Construction Inspector: Kyle Schlink, Public Works
Estimated Construction Cost - $6,999,000
Estimated Schedule – September 2017 – November 2018


Construction of Wheelock Drive NE - J7814

The City of Rochester will construct Wheelock Drive NE from the temporary cul-de-sac near Fire Station #2 to an intersection with E Circle Drive NE. The project includes grading, installation of utilities (water, storm sewer and sanitary sewer), and asphalt paving of a 36-foot wide street with concrete curb and gutter. 

Construction began with tree clearing on April 4, 2017 and the majority of the construction will be complete by October 7, 2017. However, due to the time required to allow settlement of the large amount of fill dirt needed for the southern end of the project, the connection to E Circle Dr NE will not be paved and completed until July 28, 2018. 

Continue to check this website for updates.  Last updated: April 8, 2017.

Project Contact: Brett Jenkinson, Public Works (507-328-2466) 


Storm Sewer Improvements on 14th Ave NE - J6681

 Project Manager:  Matt Crawford, Public Works
Construction Inspector:  Eric Loftus, Public Works
Construction Start:  Monday, October 9th
Construction Completion:  Wednesday, November 15th