2017 Construction Activity

 

2017 Sidewalk Replacement & Repair - J4699 Phase I & J4702 Phase II

Project Manager: John Wellner, Public Works Construction Inspector:  Travis Dunn, Public Works

18th Avenue NW (CR 112) Reconstruction from 37th Street NW to 55th Street NW – J7813

18th Avenue NW, also known as County Road (CR) 112, provides a critical connection in the growing northwest corner of Rochester. As the community has grown north to 55th Street NW and beyond, the traffic on 18th Avenue NW has also increased. The goal of this project is to reconstruct 18th Avenue NW to improve the function and safety of the roadway for pedestrians, bicycles, transit and vehicles while better serving the surrounding urbanizing land uses.

The proposed project includes reconstruction of 18th Avenue NW (CR 112) from 37th Street NW to Royal Place NW and pavement rehabilitation from Royal Place NW to 55th Street NW. The proposed project will replace deteriorated pavement, replace existing signal systems, address aging sanitary sewer and water main utilities, provide pedestrian enhancements, improve the storm drainage system, construct an urban section with a mini roundabout, add bike lanes, and add landscaped medians for access management improvements.

For more information on the project planning and design that led to this construction project, please visit Bolton-Menk 18th Avenue NW (CR112) Reconstruction Project

Project Updates

Project Manager/Construction Manager: Dillon Dombrovski, Public Works
Construction Inspector: Kyle Schlink, Public Works
Estimated Construction Cost - $6,999,000
Estimated Schedule – September 2017 – November 2018


 

55th Street NW Improvements from 50th Avenue NW to West Circle Drive (CSAH 22) - J9644/J9856

55th Street NW will be reconstructed from 50th Avenue NW to West Circle Drive, including new signals, pedestrian facilities, bike lanes and stormwater improvements. 55th Street NW will have a new alignment between Fairway Drive and West Circle Drive, where it will intersect West Circle Drive (CSAH 22) at Members Parkway NW. The existing 55th Street connection to West Circle Drive will be replaced with a cul-de-sac approximately 400’ east of Fairway Drive. New traffic signals will be placed at the intersections with 44th Avenue NW, Fairway Drive NW (on the new alignment), and at West Circle Drive/Members Parkway NW. The project construction cost is $6.7M and is funded using Federal Aid funds, State Aid funds and local utility funds.

The project is scheduled for construction to begin on June 8, 2016. The project will continue into 2017, with an anticipated completion date of September 1, 2017. It will have a major impact on those who travel this corridor, with road closures and lane restrictions being the most common impact. The first stage will close the roadway between 50th Avenue NW and 44th Avenue NW, including the intersection at 44th Avenue NW. The second stage will be from 44th Avenue NW to just east of Rhino Linings, and this stage will be constructed in two halves. Traffic during Stage 2 will only be allowed in the westbound direction along this segment. Stage 3 includes the grading of the new alignment to the south of the VA Clinic. This stage and others will have less travel restrictions, but drivers should always be cautious and follow all traffic control signage. Detours will be along Valleyhigh Drive (CSAH 4) and 65th Street NW to 50th Avenue NW for those travelers that wish to avoid the project area altogether.

This work will impact the city bus routes and schedules, so bus riders should pay close attention to changes that will be posted at bus stops along this project and surrounding areas.

Project No: M1-88
Project Manager: Doug Nelson, Public Works
Construction Supervisor: Dillon Dombrovski, Public Works
Construction Inspectors: Tim Klein, Public Works
Current Project Schedule:
           Bid Project - April 2016
           Award Project - May 2016
           Construction Start - June 2016
           Construction Completion - August 2017


Rehab / Mill / Overlay Park Lane SE - J7297

Project No: M14-41
Project Manager: Dillon Dombrovski, Public Works
Construction Inspector:  Eric Loftus, Public Works


Construction of Wheelock Drive NE - J7814

The City of Rochester will construct Wheelock Drive NE from the temporary cul-de-sac near Fire Station #2 to an intersection with E Circle Drive NE. The project includes grading, installation of utilities (water, storm sewer and sanitary sewer), and asphalt paving of a 36-foot wide street with concrete curb and gutter. 

Construction began with tree clearing on April 4, 2017 and the majority of the construction will be complete by October 7, 2017. However, due to the time required to allow settlement of the large amount of fill dirt needed for the southern end of the project, the connection to E Circle Dr NE will not be paved and completed until July 28, 2018. 

Continue to check this website for updates.  Last updated: April 8, 2017.

Project Contact: Brett Jenkinson, Public Works (507-328-2466)


 

1st Avenue NE/SE Sanitary Sewer Relief Line Phase A J7825 and Rochester Parking Ramp No.6 J2582

Road Closure Maps:

Overall Project Manager: John Pristash, Kraus-Anderson Construction Company (507-218-2639)
Sewer Project Manager: Matt Crawford, Public Works
Sewer Project Inspector: Eric Loftus, Public Works

**Click here for information on the Hilton Hotel Project that is in this same area**